40 TPH boiler
Installed tonnes per hour

EP Dryden was responsible for the supply, installation and commissioning of the steam plant, with an integrated control system. The scope of service was later expanded to include the operation and maintenance of the steam plant.

DATE: March 2019


LOCATION: Nokeng – North of Pretoria


NOMINAL POWER: 4 x 10T/h boilers


TECHNOLOGY USED: Cochrane Mk7, 10T/hr, 10 Barg, coal fired boilers


FUNDING OPTION: Phase 1: Cash Purchase Agreement; Phase 2: Multi-year Steam Outsource agreement whereby EP sells steam on a Rand-per-ton basis

Project Background

The Project for the manufacture, installation and commissioning of a new steam generation plant was awarded to EP Dryden by the main contractor, DRA Projects SA